Mapitsi Civil Works

Rand Water

Zuikerbosch Infrastructure Works

Project type

Water infrastructure programme

Client
Rand Water

Project summary

A grouped programme of pipeline, access-steelwork and concrete-rehabilitation packages at Rand Water facilities.

Major scope

The programme spans new pipeline construction, structural steelwork, concrete rehabilitation and integrated mechanical and automation interfaces.

  • Large-diameter outlet and wash-water pipeline works
  • Safety platforms and access steelwork
  • Concrete joint and process-structure rehabilitation
  • Sludge pipeline installation, automation and commissioning

Programme packages

Coordinated scopes at Zuikerbosch.

P.02550

Emergency Overflow, River Outlet and Wash-Water Pipelines

  • Approximately 331 metres of new DN1200 pipeline
  • Outlet structure discharging into the Vaal River
  • Approximately 2,200 metres of new HDPE wash-water pipeline
  • Valves and fire hydrants

P.05581

Safety Platforms and Access Steelwork

  • Design, supply and installation around sedimentation tanks
  • Replacement of spiral plates

P.04531

Process-Structure Concrete Rehabilitation

  • Wall-joint repairs and concrete works
  • Sedimentation tanks, flocculators and flash mixers at Works Area 1

P.05578

Panfontein DN800 Sludge Pipeline

  • 220-metre DN800 sludge pipeline
  • Valve chambers, actuation and automation
  • Testing and commissioning

Project enquiry

Discuss comparable infrastructure requirements.

Contact our team