Johannesburg Water
Crosby Bulk Water Infrastructure
Bulk pumping mains, a backup pump station and pump-station refurbishment linking Rand Water take-off, Crosby Reservoir, Crosby pump station, Hursthill and Brixton.
- Project number
- JW14340
- Contract value
- R358 622 841.93
- Client
- Johannesburg Water
Project summary
Bulk pumping mains, a backup pump station and pump-station refurbishment linking Rand Water take-off, Crosby Reservoir, Crosby pump station, Hursthill and Brixton.
Major scope
A live Johannesburg Water bulk-water programme combining large-diameter welded steel mains, trench installation in suburban streets, and mechanical refurbishment of Crosby and Brixton pump stations.
- Ø600 mm × 1 200 m welded steel pumping main, Crosby pump station to Hursthill Reservoir
- Ø1 000 mm × 3 400 m welded steel pumping main, Rand Water take-off to Crosby Reservoir
- 600 mm bypass
- 600 ℓ/s backup pump station
- Refurbishment of Crosby pump station, retrofitted to Brixton and Hursthill
- Refurbishment of Brixton Reservoir pump station
Project gallery